If a manager would like to have four workstations in a meat-processing plant. If the processing requires three consecutive tasks, starting with task one taking 3 minutes, task two taking 6 minutes and task three taking 8 minutes. What should be the optimal cycle time? Select one: O a None of the answers Ob 3.50 Oc 4.25 Od 3.50 O e. 3.75 In a financial portfolio planning office, two consecutive tasks must be completed. The first task takes 11 minutes the second takes 18 minutes. If the cycle time is calculated to be 8 minutes. What should be the minimum number of work stations? Select one: O a 5.00 Ob. 3.63 Oc. 3.75 Od. None of the answers O e. 4
 